Hi, I'm Mary Knox, a Cheyenne native, Realtor and Associate Broker with Coldwell Banker – The Property Exchange. I work with people who already live here and with people moving to Cheyenne from somewhere else. Lately I've had a lot of questions about the data centers going up around town. Here's a straightforward look at what's public and current as of November 2026.
Cheyenne isn't new to data centers
Microsoft built its first Cheyenne datacenter in 2012 and has been part of the community for more than 14 years. Smaller operators, including Lunavi in the Cheyenne Business Parkway, have been here for years as well.
What is new is the scale. As of May 2026, Cheyenne had 10 data centers of all sizes already operating, five under construction, and nine in planning. Several of those planned projects have moved forward since then. Here are the largest named projects around Cheyenne and Laramie County.
The major projects around Cheyenne
Microsoft. In April 2026, Microsoft announced plans to buy about 3,200 acres for a Cheyenne expansion, including about 200 acres in Bison Business Park on Wapiti Trail and a larger tract east of South Greeley Highway. On July 13, 2026, City Council annexed about 3,460 acres in that area, south of Sweetgrass. Build-out is expected to take 10 to 20 years. In November 2026, a petition challenging the annexation did not have enough valid signatures, so the annexation remains in place. As of June 2026, Microsoft had more than 320 full-time employees in Cheyenne, with hundreds more full-time roles expected.
Meta. Meta announced its Cheyenne campus in July 2024: 715,000 square feet in the High Plains Business Park, between I-25 and South Greeley Highway, south of College Drive. It is a $1.2 billion project that broke ground in 2024.
Related Digital and CoreWeave. In October 2025, Related Digital broke ground on a 115-acre campus in the Cheyenne Business Parkway. Phase I is a $1.2 billion, 184,000-square-foot building, with CoreWeave as the anchor tenant, scheduled for completion in late 2026. Related Digital is also the lead construction developer for Google's Project Tembo, a separate campus.
Google's Project Tembo. This is Google's first Wyoming data center. It began as a Crusoe and Tallgrass Energy project. On November 5, 2026, Google announced a $17 billion investment with Tallgrass, Black Hills Energy, American Electric Power, and Related Digital. In November 2026, Google acquired the site from Crusoe. The campus is planned on about 700 acres in Laramie County, next to U.S. Highway 85, with four data center buildings. Site work is planned as early as the end of 2026, some data halls in the second half of 2028, and full build-out around the end of 2031. In October 2026, Black Hills Corp. signed agreements to serve the planned campus and plans to invest $1.8 billion in new company-owned generation between 2027 and 2029.
Skybox and ViaWest at Cox Ranch. On September 28, 2026, City Council annexed and rezoned about 1,260 acres of the Cox Ranch property west of Roundtop Road. The plan includes two to three buildings near Happy Jack Road and the North Range Business Park, and a five-to-seven-year construction period. The project still needs more approvals and is years from groundbreaking.
Vantage's Project Latigo. On September 1, 2026, Laramie County commissioners approved a Planned Unit Development zone change for an about 1,835-acre campus about 12 miles from Cheyenne, near Terry Ranch Road between Interstate 25 and U.S. Highway 85. The planned investment is $4 billion to $20 billion. The first phase is planned for 2027 through 2030, with four data center buildings, on-site workforce housing, and as many as 2,000 jobs. A zone change is not the last step, and construction had not started as of that approval.
Other data center proposals exist in Wyoming outside Laramie County. Those are not covered here.
Construction jobs and permanent jobs are very different
If you add up every number in the announcements, it can sound as if Cheyenne is about to add tens of thousands of permanent residents overnight. That's not what the public figures show.
Construction workforces can be large: more than 1,000 skilled-trade workers at peak at Meta, more than 700 in Related Digital's first phase, about 2,500 at peak for Google, 1,000 to 1,500 at peak for Cox Ranch, and thousands of skilled tradespeople over several years for Microsoft's expansion. Those jobs are temporary, they overlap on different calendars, and not all of those workers will live in Cheyenne long term.
Permanent on-site jobs are much smaller: about 100 at Meta, 40 in Related Digital's first phase, about 250 at Google, Microsoft's current 320-plus employees with hundreds more expected, and 300 to 500 at Cox Ranch. Project Latigo is planned for as many as 2,000 jobs. I am not adding those numbers into one total, because they cover different years and some projects are still in planning.
What this can mean for housing
I won't predict home prices or promise that property values will go up. Nobody can honestly do that.
A large construction workforce, even a temporary one, can put pressure on rentals and short-term lodging. Laramie County now requires large industrial projects, including data centers, to house construction workers outside the local housing market — on site or through another county-approved arrangement — so those temporary crews do not tighten the existing supply. That requirement applies to construction-period workers, not to the people who will work at a campus once it is running. Permanent employees will still be looking for a regular place to rent or buy in Cheyenne and nearby communities. Related Digital also donated $3.5 million to help with affordable and attainable housing efforts.
If you already live here, you may notice more people touring homes near the campuses — along South Greeley Highway and I-25, and out toward Roundtop Road and Happy Jack Road near Cox Ranch. If you are moving here for one of these jobs, I wrote a separate guide on commute areas, renting versus buying, and buying a home from out of state. For a broader look at town, see Where to Live in Cheyenne and Moving to Cheyenne. Current listings are at Homes for Sale in Cheyenne.
If you want a local take
I've lived in Cheyenne for most of my life, and I know this has been a lot for our community to take in. Some people are glad to see the jobs and the tax base. Others have real questions about water, traffic, and how quickly these projects are moving. I'm not here to sell you a talking point either way. I want you to have a clear picture of what's underway, what's been approved, and what is still in planning.
If you have questions about buying, selling, or relocating, I handle every client personally. Call or text me at 307-631-1922. You'll reach me, not an assistant.
Frequently asked questions
How many data centers are coming to Cheyenne?
Cheyenne already has data centers, including Microsoft's campus dating to 2012. As of May 2026, 10 data centers of all sizes were operating, five were under construction, and nine were in planning. Since then, several large projects have moved ahead, including Microsoft's annexation south of Sweetgrass, Google's Project Tembo, the Cox Ranch annexation, and the Project Latigo zone change. Some of these campuses are already operating or under construction. Others are still in planning.
How many jobs will these projects create?
It depends on the project, and construction jobs are very different from permanent jobs. At peak construction, Meta has more than 1,000 skilled-trade workers and about 100 operational jobs; Related Digital's first phase has more than 700 construction jobs and 40 permanent jobs; Google's Project Tembo is planned for about 2,500 construction jobs at peak and about 250 operational jobs; and Microsoft already has 320-plus Cheyenne employees, with hundreds more full-time roles expected over a multi-year expansion. Cox Ranch is planned for 1,000 to 1,500 peak construction jobs and 300 to 500 permanent jobs. Project Latigo is planned for as many as 2,000 jobs. These numbers should not be added into one total.
Will data centers make it harder to find a home or a rental in Cheyenne?
A large temporary construction workforce can put pressure on rentals and short-term lodging. Laramie County now requires large industrial projects to house construction crews outside the local housing market, so those workers do not tighten the existing supply. Permanent employees will still look for regular housing in Cheyenne and nearby communities. I will not predict home prices or promise that values will rise.
Where are the main data center campuses?
Meta is in the High Plains Business Park, between I-25 and South Greeley Highway, south of College Drive. Microsoft's expansion is east of South Greeley Highway, south of Sweetgrass. Related Digital is in the Cheyenne Business Parkway. Google's Project Tembo is planned next to U.S. Highway 85 in Laramie County. Project Latigo is planned about 12 miles from Cheyenne, near Terry Ranch Road between I-25 and U.S. Highway 85. The Cox Ranch project is west of Roundtop Road, near Happy Jack Road and the North Range Business Park.
I'm moving to Cheyenne for a data center job. Can you help me find a home?
Yes. I handle every client personally, including people buying from another state. Call or text me at 307-631-1922. You can also start with my guide on moving to Cheyenne for a data center job and the Moving to Cheyenne page.
Sources
- Microsoft, "Microsoft announces intent to expand datacenter operations in Cheyenne," April 14, 2026, updated June 8, 2026. — checked November 23, 2026
- City of Cheyenne, "Petition challenging annexation falls short of signature requirement," November 10, 2026. — checked November 23, 2026
- Wyoming Tribune Eagle, "Cheyenne City Council approves Microsoft's 3,460-acre annexation after hours of public debate," July 14, 2026, updated July 15, 2026. — checked November 23, 2026
- Cap City News, "Cheyenne is 3,500 acres larger after approving controversial Microsoft annexation," July 14, 2026. — checked November 23, 2026
- Meta Data Centers, "Hello, Cheyenne!," July 2, 2024. — checked November 23, 2026
- Meta Data Centers, United States locations page (Cheyenne — checked November 23, 2026
- City of Cheyenne Planning Commission staff report, PLN-22-00010, October 3, 2022 — checked November 23, 2026
- Related Digital, "Related Digital breaks ground on 302 MW data center campus in Cheyenne, Wyoming," October 7, 2025. — checked November 23, 2026
- Google, "Google’s data center investment in Wyoming," November 5, 2026. — checked November 23, 2026
- Crusoe, "Crusoe Announces Wyoming Data Center Campus Update," November 6, 2026. — checked November 23, 2026
- County 17 / Cap City News, "Google, stepping in for Crusoe, pitches 700-acre data center campus to Laramie County," September 11, 2026. — checked November 23, 2026
- Black Hills Corp., SEC Exhibit 99.1, "Black Hills Corp. Executes Definitive Agreements to Serve Google’s Planned Data Center in Cheyenne, Wyoming," October 6, 2026. — checked November 23, 2026
- Cap City News, "Cheyenne approves 1,260-acre Cox Ranch addition after final vote," September 28, 2026. — checked November 23, 2026
- Wyoming Tribune Eagle, "Cox Ranch data center developers outline project, commitments at Cheyenne City Council work session," September 3, 2026. — checked November 23, 2026
- Cap City News, "Vantage data center gets zone change OK from Laramie County on Tuesday," September 1, 2026. — checked November 23, 2026
- Wyoming Tribune Eagle, "Industrial development boom drives Laramie County’s new workforce housing requirement," October 8, 2026. — checked November 23, 2026
- City of Cheyenne, Planning and Development, "Data Centers" (includes the May 2026 counts and the Related Digital $3.5 million housing donation). — checked November 23, 2026